June 2024
After the demolition, the walls of the cellar were started using the cutter soil mix method (CSM).
In this method, the existing soil is mixed vibration-free with cement mix, so that a constructive wall is obtained
After the demolition, the walls of the cellar were started using the cutter soil mix method (CSM).
In this method, the existing soil is mixed vibration-free with cement mix, so that a constructive wall is obtained
The first floor is almost finished. Now, only one layer is missing, including the sloped roof.
The formwork for the ground floor has been made and then the floor has been poured
The basement walls and columns in the basement were poured in early 2025