The latest news about the construction of Hotel The Dunes

On the way to a new hotel !

On this page we would like to keep you informed of the latest news regarding the construction of Hotel The Dunes. We regularly share updates on the progress of the work, important milestones and other developments that you do not want to miss. In addition, we will give you an exclusive preview of what the hotel will look like.

The latest news

September 2025

The roof structure is underway, and the first dormers and roof elements have been successfully installed. The completion of the structural phase is now in sight.

Read more

August 2025

The interior walls are finished. Now the roof can be added.

Read more

July 2025

The first floor is almost finished. Now, only one layer is missing, including the sloped roof.

Read more

May/June 2025

The interior walls of the ground floor and the 1st floor are almost finished

Read more

March/April 2025

The formwork for the ground floor has been made and then the floor has been poured

Read more

January/February 2025

The basement walls and columns in the basement were poured in early 2025

Read more

December 2024

Pouring the basement floor

Read more

November 2024

In November, work began on laying the foundation stone for the basement.

Read more

Stay close. Be the first to receive news about the opening of The Dunes, special packages, and memorable moments by the sea.

Follow The Dunes on Instagram

Hotel the Dunes

Herenstraat 124357 AL DomburgThe Netherlandsinfo@hotelthedunes.com